AS 3700 Masonry Structures Explained

G’day everyone! I’m a building inspector here in Perth, and honestly, I wish I had a dollar for every time someone’s asked me about masonry standards. Whether it’s at the local hardware store on a Saturday morning or during a site inspection, the questions keep coming: “Do I really need to follow AS 3700?” “What’s the big deal with brick standards anyway?” “Can’t I just build it like my mate did?”

Let me tell you straight up – masonry might look simple, but getting it wrong can cost you big time. I’ve seen beautiful Perth homes with cracks you could fit your finger through, retaining walls that look like they’re doing the wave, and coastal properties where the mortar’s practically disappeared thanks to salt air.

Table of Contents

What is AS 3700 and Why Should You Care?

Right, so AS 3700 is basically the bible for building with bricks, blocks, and stone in Australia. Think of it as the recipe book that tells you how to mix the ingredients properly so your wall doesn’t fall down or crack up.

Now, I know what you’re thinking – “More government red tape, right?” Wrong. This standard exists because I’ve personally inspected houses where corners were cut, and trust me, it’s not pretty. Last month alone, I saw a retaining wall in Claremont that was leaning like the Tower of Pisa because someone thought they knew better than the engineers who wrote these rules.

The thing is, timber framing will usually tell you pretty quickly if something’s wrong – you’ll hear creaking, see sagging, that sort of thing. But masonry? It can take years for problems to show up, and by then you’re looking at serious money to fix it. I’m talking about structural repairs that can cost more than a new car.

This stuff matters whether you’re an engineer designing a shopping center, an architect specifying materials for a new house, a builder trying to get the job done right, or a homeowner who just wants their investment to last. Even if you’re not swinging the hammer yourself, knowing the basics means you can have proper conversations with your tradies and spot when something doesn’t look right.

What Does AS 3700 Actually Cover?

The standard covers three main types of masonry work, and I’ll explain them in plain English:

  • Unreinforced masonry is your bread and butter stuff – the brick veneer on most Perth homes, garden walls, internal walls that separate rooms. No steel reinforcement, just good old-fashioned bricks and mortar doing their thing. Most of what I inspect falls into this category.
  • Reinforced masonry is where we add steel bars (rebar) for extra grunt. Think retaining walls holding back your sloping block, or commercial buildings that need extra strength. The steel goes in specific places and specific sizes – it’s not a “she’ll be right” situation.
  • Confined masonry is the heavy-duty stuff where masonry gets surrounded by concrete or steel elements. You’ll mainly see this in big commercial jobs, not your typical house extension.

As for materials, we’re talking clay bricks (those classic Perth red ones you see everywhere), concrete blocks, calcium silicate bricks, and AAC blocks (the lightweight ones that are getting popular). Whether you’re building a new place, adding a granny flat, or putting up a commercial building, AS 3700 sets the ground rules.

The Key Goals of AS 3700

Look, the standard has three main jobs, and they’re all about keeping you safe and saving you money in the long run:

  • Making sure your masonry can handle the load – and I mean all kinds of loads. There’s the obvious stuff like the weight of your roof and upper floors pressing down, but also sideways forces from wind. You should see some of the easterly winds we get here in Perth – they can really test a wall that wasn’t built properly.
  • Making sure it lasts in our climate – this is huge in Perth. We’ve got reactive clay that moves around like it’s got a mind of its own, salt air near the coast that loves eating mortar, and temperature swings that make materials expand and contract. I’ve seen 10-year-old walls that look 30 years old because someone used the wrong materials for Perth conditions.
  • Giving everyone the same playbook – so a wall built in Rockingham performs just as well as one in Joondalup. Consistency matters when you’re dealing with people’s safety and their biggest investment.
 

Design Principles You Need to Know

Loadbearing Design

Some walls just divide spaces, others actually hold up your house. The loadbearing ones carry weight from floors above, your roof structure, plus their own weight. AS 3700 tells you how much different wall types can safely carry based on what they’re made of, how thick they are, and what kind of mortar holds them together.

There’s also something called slenderness ratios – basically, how tall and skinny a wall can be before physics says “nope.” I see DIY retaining walls all the time that ignore this principle. They might look OK for a year or two, then start bulging or just give up entirely. Last winter, I inspected one in Subiaco that looked like it was six months pregnant – not a good look.

Reinforced vs Unreinforced Masonry

Most house stuff uses unreinforced masonry. Your typical single-brick garden wall, double-brick feature wall, the brick veneer on timber-framed homes – no steel needed, just solid construction.

But sometimes you need the extra strength that steel reinforcement provides. Retaining walls over a certain height, areas carrying heavy loads, or where the engineer specifically calls for it. The trick is getting the steel in the right places and the right sizes. I’ve seen people just shove some mesh in there thinking it’ll help – usually makes things worse because they haven’t thought about how forces actually move through the wall.

Lateral Loads and Wind Resistance

Perth’s position means we cop some serious wind, especially if you’re anywhere near the coast. Scarborough, Cottesloe, Fremantle – these areas see winds that can really test your construction.

AS 3700 addresses this through proper connections between walls and the rest of your structure. Your walls need to be tied to floors and roofs properly so they can resist wind trying to push them over or suck them off. I’ve been to properties after big storms where walls have literally separated from the house because these connections weren’t done right.

Durability Classifications

This bit’s really important for Perth conditions. The standard divides the world into exposure zones:

Zone A is the mild stuff – inland areas where weather’s pretty normal Zone B is moderate – some moisture exposure but nothing too harsh
Zone C is the severe zone – coastal areas getting salt spray, or anywhere with aggressive soil conditions

Here’s the thing – heaps of Perth falls into Zone C because of our coastal location and reactive soils. If you’re anywhere from Hillarys down to Mandurah and close to the ocean, you’re probably in Zone C. Even some inland areas qualify because of soil conditions.

Using Zone A materials in a Zone C location is like wearing thongs to a black-tie event – technically they’re both shoes, but they’re not right for the job.

Construction Requirements That Matter

Wall Thickness

The standard’s pretty clear about minimum wall thicknesses. A single-brick wall (110mm) might be fine for your garden wall, but if you’re building something structural, you’ll often need double brick (230mm) or more.

I see people trying to save money by going thinner than required. False economy – you’ll either fail inspection or end up with problems down the track.

Mortar Requirements

Mortar gets classified from M1 through M4, with M4 being the strongest. Which one you need depends on where you’re building and what loads the wall’s carrying.

Here’s where I see corners cut all the time – someone uses M2 mortar where M3 is required because it’s a bit cheaper or easier to get. Might save you 50 bucks today, but it could cost you thousands later when the wall fails prematurely.

Control Joints and Movement

Masonry moves. Hot weather makes it expand, cold weather makes it contract, moisture makes it do weird things. AS 3700 requires control joints at specific intervals to manage this movement.

Skip these joints and you’ll get cracks – but not nice, controlled cracks where you want them. You’ll get random cracks wherever the masonry decides to let go, usually in the worst possible places. I inspected a boundary wall in Mount Lawley last year that looked like a spider web because the builder thought control joints were optional.

Wall Ties and Cavity Details

Cavity walls are really common in Perth – you’ve got an outer brick layer and an inner layer with a gap in between. The wall ties hold these layers together and they need to be the right type, spaced correctly, and installed properly.

Poor wall tie work is one of the most common problems I see. The scary thing is, you might not know there’s a problem for years, then suddenly your cavity wall starts sagging or separating. Expensive fix, and often not covered by insurance because it’s a construction defect.

Damp-Proof Courses

Perth’s clay soils can hold heaps of moisture, which wants to travel up through your masonry walls. Damp-proof courses stop this from happening, but they need to be in the right places at the right heights.

I’ve seen beautiful heritage-style homes where rising damp has destroyed internal walls because someone skipped or incorrectly installed the damp-proof course. The smell alone will drive you out of the house.

Common Problems I See on Perth Job Sites

After 15 years of inspections around Perth, these issues keep popping up:

  • Dodgy mortar – usually from people not following mixing instructions or using the wrong class for the job. I’ve scraped mortar out of joints with my fingernail because it was mixed so poorly. That’s not holding anything together.
  • Missing movement joints – builders sometimes think they’re saving time by skipping control joints. Then they wonder why there are random cracks six months later.
  • Inadequate support under heavy loads – like when someone rests a steel beam on regular bricks without proper bearing pads or lintels. The bricks aren’t designed for concentrated loads like that.
  • Wrong materials for Perth conditions – using standard bricks in high-salt coastal areas, or not upgrading materials for our reactive clay soils. I’ve seen 5-year-old walls that look ancient because the wrong materials were used.
  • Wonky walls – walls that are out of plumb, too tall for their thickness, or don’t have proper lateral support. Particularly common with retaining walls where people underestimate the forces involved.
 

How AS 3700 Fits with Other Standards

AS 3700 doesn’t work alone – it’s part of a family of standards that all work together:

The National Construction Code is what your building approval gets assessed against, and it references AS 3700 for masonry requirements.

AS 4773 covers masonry in smaller buildings and works hand-in-hand with AS 3700 for house stuff.

AS 3600 deals with concrete structures, which comes into play when you’re mixing reinforced masonry with concrete elements.

These aren’t suggestions – they’re legal requirements referenced in your building permits and engineering certificates.

Why AS 3700 is Particularly Important in Perth

Our local conditions make proper masonry work absolutely critical:

  1. Reactive clay soils – Perth’s clays expand and contract massively with moisture changes. I’ve measured seasonal movement of 50mm or more on some blocks. Your masonry needs to handle this without cracking.
  2. Coastal conditions – salt air is incredibly aggressive toward masonry materials, especially mortar joints. Plus we get higher wind loads near the ocean.
  3. Saline groundwater – much of Perth sits on saline groundwater that attacks masonry from below. Standard materials just aren’t up to the job in many areas.
  4. Temperature extremes – 40°C summer days followed by 15°C winter mornings create significant thermal movement. Your masonry design needs to accommodate this.
 

Your Masonry Inspection Checklist

Whether you’re a builder, homeowner, or just want to know what to look for, here’s what I check:

  1. Right materials for the job – are the bricks and mortar appropriate for Perth conditions and the specific location?
  2. Mortar quality – correct strength class, properly mixed, and completely filling all joints.
  3. Control joints – present where required and properly sealed against water entry.
  4. Damp-proofing – installed at correct heights and properly integrated with the wall construction.
  5. Wall ties in cavity walls – correct type and spacing, properly embedded in mortar.
  6. Steel reinforcement – where required, correctly positioned and tied according to drawings.
  7. Lintels over openings – adequate size with proper bearing on both sides.
  8. Structural connections – walls properly tied to floors, roofs, and other structural elements.
 

Getting It Right From the Start

Here’s my bottom line after years of seeing what works and what doesn’t: masonry needs to be done right the first time. You can’t easily fix masonry problems like you might fix a plumbing leak or rewire a circuit.

If you’re planning masonry work, invest in proper design and construction upfront. Use qualified tradespeople who actually understand AS 3700, not just someone who’s “been laying bricks for 20 years.” Experience matters, but so does knowledge of current standards.

Don’t try to save money on materials – the difference between appropriate and inappropriate materials is usually minimal compared to your total project cost, but massive compared to the cost of fixing failures.

For big jobs, consider independent inspections during construction, not just at the end. Catching problems while work’s in progress is always easier and cheaper than dealing with them after everything’s finished and painted.

Remember, AS 3700 isn’t some bureaucrat’s idea of fun – it’s based on decades of real-world experience, including plenty of expensive failures. Following the standard gives you the best shot at a project that’ll still look good and perform well in 20 years’ time.

If you’re ever unsure about masonry requirements, talk to a qualified structural engineer or experienced builder who knows Perth conditions. Yeah, it costs a bit for advice upfront, but it’s cheap insurance against much bigger problems later.

Stay safe, build smart, and don’t be afraid to ask questions. That’s what we’re here for.

FAQs

AS 3700 is the Australian Standard for masonry structures and sets out the design, construction, and performance requirements for buildings made with brick, block, or stone. It applies to a wide range of projects in Perth—from unreinforced masonry commonly used in residential homes, to reinforced masonry found in retaining walls and commercial construction, and confined masonry used in larger, more complex structures. Whether you're building a brick veneer home, a garden wall, or a structural retaining wall, AS 3700 legally applies when masonry forms part of the structure. Compliance ensures durability, structural integrity, and alignment with the National Construction Code.

AS 3700 covers three main types of masonry construction, each with distinct applications and requirements. Unreinforced masonry is the most common in standard Perth homes and consists of brick or block walls without internal steel reinforcement. Reinforced masonry includes steel reinforcement embedded within the masonry to provide added strength, making it ideal for retaining walls, structural boundary walls, or any walls supporting significant loads. Confined masonry involves enclosing the masonry with reinforced concrete elements and is typically used in commercial or multi-storey buildings rather than residential homes. Each type must meet specific design and construction criteria under AS 3700 to ensure structural integrity, safety, and long-term durability.

AS 3700 is especially important in Perth due to the city’s challenging environmental conditions. Reactive clay soils common in many suburbs can cause seasonal ground movement, putting stress on masonry walls. Coastal areas expose brickwork and mortar to salt-laden air, increasing the risk of salt attack and corrosion. Perth’s wide temperature fluctuations also lead to thermal expansion and contraction, which can cause cracking over time. In some locations, saline groundwater further accelerates material deterioration. AS 3700 addresses these risks through durability classifications, material selection guidelines, and construction requirements that ensure masonry structures remain strong, stable, and long-lasting in Perth’s unique climate.

AS 3700 helps prevent structural failure in masonry walls by setting out precise design and construction requirements that ensure long-term performance. It regulates wall thickness and slenderness ratios to maintain stability, and it calculates load-bearing capacity based on wall height, material strength, and mortar type. The standard also addresses resistance to lateral forces, such as wind pressure—particularly important in exposed Perth suburbs—and defines how masonry walls must be properly connected to floors, roofs, and adjoining walls to distribute loads safely. When these rules are ignored, issues like bulging, cracking, or even complete wall failure can occur—sometimes years after construction—posing serious safety and financial risks.

AS 3700 defines three durability zones—Zone A (Mild), Zone B (Moderate), and Zone C (Severe)—based on environmental exposure risks. While Zone A is rare in Western Australia, some inland Perth suburbs may fall into Zone B. However, most of coastal Perth, from Hillarys to Mandurah, is classified as Zone C, where masonry is exposed to high levels of salt, moisture, and aggressive soil conditions. In these severe environments, AS 3700 requires the use of materials specifically rated for durability under harsh exposure. Using lower-grade materials intended for Zone A in Zone C areas can lead to premature deterioration, cracking, and structural failure of masonry elements.

Common construction defects that breach AS 3700 often stem from improper materials or poor workmanship, and they can lead to serious structural and compliance issues. One frequent error is using the wrong mortar class, such as M2 when M3 or M4 is required for strength and durability. Missing movement joints can result in unsightly and unpredictable cracking, while failure to install a damp-proof course allows rising moisture to damage internal walls over time. Other issues include incorrect or missing wall ties, poor cavity construction, and unsupported structural loads, such as beams resting on masonry that isn’t designed to carry them. These defects not only compromise structural performance but can also result in failed inspections, costly rectifications, or even legal liability for the builder

AS 3700 ensures masonry structures can resist wind and lateral forces—particularly important in coastal Perth suburbs like Scarborough, Cottesloe, and Fremantle where strong winds are common. The standard requires reinforcement or increased wall thickness for tall or unsupported masonry walls to prevent failure under pressure. It also specifies tie-down connections that anchor masonry to floors and roofs, helping structures withstand uplift and lateral wind loads. Additionally, AS 3700 enforces slenderness ratio limits to prevent walls from flexing, bowing, or cracking under wind pressure. These provisions are essential to maintaining structural integrity in Perth’s exposed environments.

Movement joints are intentional gaps built into masonry walls to accommodate natural expansion and contraction caused by temperature changes, moisture variation, and structural movement. Under AS 3700, these joints are mandatory and must be spaced based on the wall’s length, height, material type, and environmental exposure—especially in areas with high thermal loads like long boundary walls or sun-exposed façades. The standard also requires proper joint sealing to prevent water ingress and maintain durability. Omitting movement joints is a common cause of unsightly and often costly cracking, making their correct placement and installation essential for long-term performance and compliance.

Wall ties, damp-proof courses (DPCs), and lintels each play a crucial role in ensuring masonry construction complies with AS 3700 and performs safely over time. Wall ties secure inner and outer leaves of cavity walls, and their spacing, embedment depth, and corrosion resistance are strictly regulated to maintain structural integrity. Damp-proof courses prevent rising moisture from entering walls and must be correctly placed—typically at least 150mm above finished ground level—to protect against internal damp and deterioration. Lintels carry the loads above openings like doors and windows, and they must have adequate bearing length and be sized correctly for the span and load. In Perth, incorrect installation of these elements is one of the most frequently identified and costly defects during inspections, often requiring major rectification if overlooked.

AS 3700 works in conjunction with several other key Australian Standards and the National Construction Code (NCC) to ensure that masonry construction is structurally sound, safe, and compliant. AS 4773 covers the construction of smaller masonry structures and complements AS 3700, particularly in residential settings. AS 3600, which governs concrete structures, often applies alongside AS 3700 when reinforced masonry elements are used. AS 2870 governs slab-on-ground foundations that support masonry walls, making it a critical companion standard. The NCC legally references AS 3700 as the primary compliance pathway for masonry design and construction. Together, these standards create a coordinated framework that ensures consistency in design, material selection, construction practices, and long-term performance.